April 18, 2017

Maple Avenue Road Closure 2017

Maple Ave Press Release

Starting May 1st, the Village of Victor will be closing Maple Ave/State Rte 444 starting at Rte 96 /Main Street to the Village line. Use School Street as the detour, signs will be posted. The only cars allowed down Maple Ave are residents and local businesses.

Construction will take most of the summer and should be completed around September 1st. Updates will be posted on the web site at www.victorny.org and on our Facebook page Village of Victor.

If there are any questions, please contact Village Hall at 585-924-3311.

Facebook Twitter Google Plus Email

Latest Update:

August 18, 2017 9:54 AM

Week of August 21:

All the driveway aprons are done, continuing to top soil and seed.

Final paving has been moved to Thurs. Aug. 24, weather permitting and the anticipated date for the road to be open is Sept. 1.

Thank you!

Prior Updates

View All Updates
August 11, 2017 8:48 AM

Week of August 14:

Monday and Tuesday, ARC and St. Pat’s driveway aprons. Continuing to top soil and seed, weather permitting.

The 25mph speed limit was approved, signs have been ordered and there will be a 25mph ahead sign installed coming down RT 444 towards Maple Ave.

Final paving has been scheduled for Tues. Aug. 22, weather permitting.

Maple Ave. is still on schedule to be opened before Labor Day.

August 4, 2017 12:42 PM

Week of August 7:

Public Hearing to lower the speed limit on Maple Avenue to 25 MPH on Monday, August 7 @ 7:00pm

Milling on Tues. August 8

Continuing to work on driveway aprons, top soil, and seeding