Willis Hill Road Capital Project

The Willis Hill Road Capital Project will begin April 10th and will go through mid-July (weather permitting). Please expect delays, plan accordingly and use caution when traveling in this area.

  • The work will take place at the intersections of Modock Road and Shire Lane to improve the site distance at both locations.
  • The Contractor will be using traffic lights to control traffic which will be in place until the project is complete and there will be a road closure to complete the paving at each intersection (will post date when known)
  • In early May, Town Highway crews will be installing culvert pipe, cleaning ditches, and widening the shoulders on Willis Hill from Dryer Road to Route 251.
  • Approx mid-June a cold-in-place recycle will be completed followed by a hot asphalt overlay.
  • Approx mid-July they will tie in all the driveways, topsoil and seed as needed for completion.

We will give more updates on any road closures, for paving operations, as the project progresses. 

Thank you for your patience during this project!

Road Construction Work Area Ahead Sign

Town of Victor Spring / Summer Highway Projects

2023 Road Construction

The following is the roadwork scheduled for this construction season:

Milling and Paving (DI & Gutterwork as needed) – Chapel Hill (Phase 1, Wellington Drive, Oak Ridge Drive, Pine Tree Drive and Bramwell Park

Crack Filling – High Street, Anton Rise, Canterbury Trail, Chestnut Hill, Dorsett Trail, Kensington Court, Taylor Rise, and Whistlestop Road

Chip sealing – Strong Road (County Road 41 to NYS 251), Modock Road, Taylor Road, Harloff Road, Malone Road (County Road 41 to Dryer Road), Turner Drive, Pilgrim Pass, and Oakwood Drive

Reprofiling – Blazey Road, Bortle Road, Brownsville Road, Cline Road, Gillis Road (County Road 9 to Cline Road), Lane Road (High Street to County Road 9), Richardson Road, and Lynaugh Road

Micropaving – Burlington Road, Golfview Rise, Hillside Drive, Rabbit Ear Pass, Silver Hill Path and Song Hill Lane

Capital Road Projects – Willis Hill Road and Railroad Mills Road (Engineering) 

Pipe Replacements – Golfview Rise, Rabbit Ear Pass, Valentown Road and Dryer Road (School Road to NY 444)

Drainage Work – Chapel Hill (Phase 1), Wellington Drive, Oak Ridge Drive, Pine Tree Drive and Bramwell Park